Answer the following questions (use MS Project help if necessary):
1) Define effort-driven?

Effort-driven scheduling extends or shortens the duration of a task to accommodate changes to resources, but doesn’t change the total work for the task.

2) Under what circumstances would you turn off effort driven scheduling?

You may have a task that is very complex or requires highly-skilled resources. Adding more resources may slow the team down if task activities need additional coordinating or if people need instruction before they can perform.

3) Use a real-world example of when you would make a task as a Fixed Duration type task?

I have a task for purchasing equipment, I know it will not take Joe all day to accomplish this, so if I want Joe to work half-time on a task, I would simply assign him at 50 percent Units.

4) What is the formula for calculating duration?

The assignment Duration (in hours) is equal to the assignment Work (in hours) divided by the assignment Units value.

5) What are the eight preset work contours (hint: In the Task Usage view right click on a resource name an open the assignment information box) and what are the procedures in applying them to a resource on a task?

The 8 present contours are: Flat - Work hours are even throughout task; Back loaded - Work increases toward end of the task; Front loaded - Work decreases toward start of the task; Double peak - Two peaks occur over task duration; Early peak - Peak activity occurs during first quarter; Late peak - Peak activity occurs during last quarter; Bell - Hours peak in the middle, hours low at start/finish; Turtle - Same as Bell, but the start/finish units are high. In Task Usage view, select the task's resource by clicking the resource name. Click the Assignment Information button on the toolbar. On the General tab in the Assignment Information…...

Similar Documents

Review Question -Mgmt404

...Review Questions Name _________________ Answer the following questions (you may use MS Project Help): 1) What are the three base calendars included in MS Project and what are the default values of each? The three base calendars are Standard, Night Shift, and 24 Hours. Standard default values is all week days from 8 AM to 12 PM then 1 PM to 5 PM. Night Shift is All week days from 12 AM to 3 AM, 4 AM to 8 AM, and 11 PM to 12 AM. Plus Saturday from 12 AM to 3 AM, and 4 AM to 8 PM. 24 Hours is every day from 12 AM to 12 AM. 2) What is the difference between a base calendar and a resource calendar? A bade calendar is for everyone to use while a resource calendar is only for that resource that was assigned to. 3) Why schedule one project meeting after completion of the last task, Test System? Since we were working out the work days in the schedule, it lower the finish date on the project. But since the last project meeting was set to this date it could not be changed. So when we delete it, the project days lower down. 4) Give an example of when you would assign a 24-hour calendar to a resource. When we need that resource to work every day in the given time we need them to. For example a securities guard. 5) If you were doing a senior project, what would be the base calendar you would use for students working on the project and what adjustments would you make to it? If I was working on a senior project there is no set time on when......

Words: 320 - Pages: 2

Mgmt404 Week 1

...Review Questions Name __Jerry Valentino Answer the following questions (use MS Project Help, if necessary): 1. What is the difference between a main summary task and a summary task? The main summary task describes the project and has multiple tasks outlined below it. In this week 1 lab, Jay Bongcaron’s New System is the main summary task. Summary task are subordinate to a main summary task. Each summary task is a description that consists of multiple tasks that are scheduled to be completed in the project. For example, this week’s lab had Proposal Creation, Vendor Selection, Implement System, and Project meeting as summary tasks. 2. On the View Tab, what does the Outline button with plus and minus signs do? If only the main summary task is showing in the Gantt chart, the plus sign will show all the subtasks below it. If all subtasks are showing, then the minus sign will collapse and hide all the tasks to only show the main summary task. 3. What is a milestone? A milestone represents an event that marks the completion of a group of related tasks. This week’s lab has a milestone of Award Contract on 11/25/2013 when the Vendor Selection summary task is completed. 4. What predefined report can you not make changes to the header and footer? This would be the project summary report 5. Give a real-world example of a) A successor task requiring lead time Placing drywall on a home usually requires waiting for an electrician......

Words: 315 - Pages: 2

Mgmt404 - Lesson2 Review Questions

...Answer the following questions: 1) What is a resource? People, equipment & materials necessary to complete a task 2) Why aren't resources assigned to summary tasks? Summary tasks are simply a grouping for a set of related tasks. The indiv tasks require resources but the summary task is just a compilation of those resources. 3) What is the difference between Start, Prorated and End in association with costs? Start – cost applied at the beginning of the task Prorated – cost applied as work is completed End – cost applied when the task is completed 4) Give a real-world example of the difference between a fixed cost and a cost per use? Give a real-world example of the difference between a fixed cost and a cost per use? Fixed Cost: (buy equipment) company bids $500 to clean carpet, cost of airline ticket… Cost Per Use: (rent equipment) Hourly rate on moving van, rental of shampoo machine, landing fee each time plane lands… 5) Why is a fixed cost entered with the task and not the resource? Because the cost is the same no matter how many people, hours, materials used. Not dependent upon the amount of time or number of resources it takes to complete. 6) Why is the resource cost for the Wiring Contractor $0.00? Because the installation of the wiring is a fixed contractual price of $4000 – it will not matter how many hours the contractor takes – still the same price. 7) Which resource is Overallocated and......

Words: 277 - Pages: 2

Mgmt 404 (Project Management) Entire Course - Devry

...com/MGMT-404-Project-Management-Entire-Course-DeVry-1123432.htm?categoryId=-1 If You Face Any Problem E- Mail Us At JohnMate1122@gmail.com MGMT404 Week 1 iLab MGMT404 Week 1 DQ 1 Case Study; A Day in the Life MGMT404 Week 1 DQ 2 Case Study; Moss and McAdams Accounting Firm MGMT404 Week 2 Course Project: Project Selection MGMT404 Week 2 iLab MGMT404 Week 2 DQ 1 Project Scope MGMT404 Week 2 DQ 2 Case Study; Sharp Printing AG MGMT404 Week 3 Course Project: Scope Statement MGMT404 Week 3 iLab MGMT404 Week 3 DQ 1 Project Schedule MGMT404 Week 3 DQ 2 Risk Management MGMT404 Week 4 Course Project: Work Breakdown Structure and Network Diagram MGMT404 Week 4 iLab MGMT404 Week 4 DQ 1 Managing Resource Constraints MGMT404 Week 4 DQ 2 Reducing Project Duration MGMT404 Week 5 Course Project: Risk Management Plan MGMT404 Week 5 iLab MGMT404 Week 5 DQ 1 Project Baseline MGMT404 Week 5 DQ 2 Project Communication MGMT404 Week 6 Course Project: Resource Management Plan MGMT404 Week 6 iLab MGMT404 Week 6 DQ 1 Case Study; Western Oceanography Institute MGMT404 Week 6 DQ 2 Case Study; Kerzner Office Equipment MGMT404 Week 7 Course Project: Communication Plan MGMT404 Week 7 iLab MGMT404 Week 7 DQ 1 Case Study; Buxton Hall MGMT404 Week 7 DQ 2 Case Study; A Day in the Life revisited MGMT404 Week 8 Final Project Package...

Words: 256 - Pages: 2

Mgmt404 Week 5

...What Am I Worth? DeVry University What Am I Worth? There is a balancing act that has to happen periodically in the work place in order for the employees to be happy and fairly compensated and for a business to stay afloat. In the application case: “Appraising the Secretaries at Sweetwater U” the balance was in danger of being tipped when the university realized that there was a bias that was occurring during annual job performance appraisals. Because these appraisals were directly tied to annual income raises, these biases proved to be very costly to the university since every appraisal led to a maximized income raise for every secretary at Sweetwater U. In this scenario, the secretaries at Sweetwater U were happy but the University’s budget was not. After newly appointed Vice President for administrative affairs Rob Winchester met with his experts at Sweetwater U, they presented him with two ideas that were viable ideas but in my opinion, insufficient. The first recommendation that Winchester’s experts gave was to change the rating form that was being used by the administrators to appraise their secretaries. The second idea that was presented to Vice President Winchester was to sever the tie which directly linked the secretaries’ rating forms to their annual income raises. One agreeable aspect to changing the rating form would allow an unbiased rating system to be developed so that the rating form would have some form of value with consideration to......

Words: 888 - Pages: 4

Mgmt 404 Project Management Entire Course

...lancehomework@gmail.com MGMT404 Week 2 Project Selection MGMT 404 Week 3 Scope Statement MGMT 404 Week 4 Work Breakdown Structure and Network Diagram MGMT 404 Week 5 Risk Management Plan MGMT 404 Week 6 Resource Management Plan MGMT 404 Week 7 Project Coffee Shop Communication Plan MGMT 404 Week 8 Course Project MGMT 404 Complete Course Weeks 1-7 iLabs MGMT404 Week 1 iLab Basics of Project Scheduling MGMT404 Week 2 iLab Managing Project Resources MGMT404 Week 3 iLab Scheduling with Resources MGMT404 Week 4 iLab Working with Calendars MGMT404 Week 5 iLab Resource Workloads MGMT404 Week 6 iLab Task Constraints and Baselines MGMT404 Week 7 iLab Tracking Project Progress MGMT 404 Project Management Entire Course To Buy this Class Copy & paste below link in your Brower http://homeworklance.com/downloads/mgmt-404-project-management-entire-course/ Or Visit Our Website Visit : http://homeworklance.com Email Us : lancehomework@gmail.com MGMT404 Week 2 Project Selection MGMT 404 Week 3 Scope Statement MGMT 404 Week 4 Work Breakdown Structure and Network Diagram MGMT 404 Week 5 Risk Management Plan MGMT 404 Week 6 Resource Management Plan MGMT 404 Week 7 Project Coffee Shop Communication Plan MGMT 404 Week 8 Course Project MGMT 404 Complete Course Weeks 1-7 iLabs MGMT404 Week 1 iLab Basics of Project Scheduling MGMT404 Week 2 iLab Managing Project Resources MGMT404 Week 3 iLab......

Words: 2942 - Pages: 12

Mgmt 404 Project Management Entire Course

...Management Entire Course MGMT404 Week 2 Project Selection MGMT 404 Week 3 Scope Statement MGMT 404 Week 4 Work Breakdown Structure and Network Diagram MGMT 404 Week 5 Risk Management Plan MGMT 404 Week 6 Resource Management Plan MGMT 404 Week 7 Project Coffee Shop Communication Plan MGMT 404 Week 8 Course Project MGMT 404 Complete Course Weeks 1-7 iLabs MGMT404 Week 1 iLab Basics of Project Scheduling MGMT404 Week 2 iLab Managing Project Resources MGMT404 Week 3 iLab Scheduling with Resources MGMT404 Week 4 iLab Working with Calendars MGMT404 Week 5 iLab Resource Workloads MGMT404 Week 6 iLab Task Constraints and Baselines MGMT404 Week 7 iLab Tracking Project Progress MGMT 404 Project Management Entire Course To Buy this Class Copy & paste below link in your Brower http://homeworklance.com/downloads/mgmt-404-project-management-entire-course/ Or Visit Our Website Visit : http://homeworklance.com Email Us : lancehomework@gmail.com MGMT 404 Project Management Entire Course MGMT 404 Project Management Entire Course MGMT404 Week 2 Project Selection MGMT 404 Week 3 Scope Statement MGMT 404 Week 4 Work Breakdown Structure and Network Diagram MGMT 404 Week 5 Risk Management Plan MGMT 404 Week 6 Resource Management Plan MGMT 404 Week 7 Project Coffee Shop Communication Plan MGMT 404 Week 8 Course Project MGMT 404 Complete Course Weeks 1-7 iLabs MGMT404 Week 1 iLab Basics of Project Scheduling MGMT404 Week 2 iLab Managing......

Words: 2880 - Pages: 12

Mgmt 404 Project Management Entire Course

...Management Entire Course MGMT404 Week 2 Project Selection MGMT 404 Week 3 Scope Statement MGMT 404 Week 4 Work Breakdown Structure and Network Diagram MGMT 404 Week 5 Risk Management Plan MGMT 404 Week 6 Resource Management Plan MGMT 404 Week 7 Project Coffee Shop Communication Plan MGMT 404 Week 8 Course Project MGMT 404 Complete Course Weeks 1-7 iLabs MGMT404 Week 1 iLab Basics of Project Scheduling MGMT404 Week 2 iLab Managing Project Resources MGMT404 Week 3 iLab Scheduling with Resources MGMT404 Week 4 iLab Working with Calendars MGMT404 Week 5 iLab Resource Workloads MGMT404 Week 6 iLab Task Constraints and Baselines MGMT404 Week 7 iLab Tracking Project Progress MGMT 404 Project Management Entire Course To Buy this Class Copy & paste below link in your Brower http://homeworklance.com/downloads/mgmt-404-project-management-entire-course/ Or Visit Our Website Visit : http://homeworklance.com Email Us : lancehomework@gmail.com MGMT 404 Project Management Entire Course MGMT 404 Project Management Entire Course MGMT404 Week 2 Project Selection MGMT 404 Week 3 Scope Statement MGMT 404 Week 4 Work Breakdown Structure and Network Diagram MGMT 404 Week 5 Risk Management Plan MGMT 404 Week 6 Resource Management Plan MGMT 404 Week 7 Project Coffee Shop Communication Plan MGMT 404 Week 8 Course Project MGMT 404 Complete Course Weeks 1-7 iLabs MGMT404 Week 1 iLab Basics of Project Scheduling MGMT404 Week 2 iLab Managing......

Words: 1760 - Pages: 8

Mgmt 404 Project Management Entire Course

...Description: MGMT404 Week 2 Project Selection MGMT 404 Week 3 Scope Statement MGMT 404 Week 4 Work Breakdown Structure and Network Diagram MGMT 404 Week 5 Risk Management Plan MGMT 404 Week 6 Resource Management Plan MGMT 404 Week 7 Project Coffee Shop Communication Plan MGMT 404 Week 8 Course Project MGMT 404 Complete Course Weeks 1-7 iLabs MGMT404 Week 1 iLab Basics of Project Scheduling MGMT404 Week 2 iLab Managing Project Resources MGMT404 Week 3 iLab Scheduling with Resources MGMT404 Week 4 iLab Working with Calendars MGMT404 Week 5 iLab Resource Workloads MGMT404 Week 6 iLab Task Constraints and Baselines MGMT404 Week 7 iLab Tracking Project Progress MGMT 404 Project Management Entire Course Follow Link Below To Get Tutorial http://homeworklance.com/downloads/mgmt-404-project-management-entire-course/ Description: MGMT404 Week 2 Project Selection MGMT 404 Week 3 Scope Statement MGMT 404 Week 4 Work Breakdown Structure and Network Diagram MGMT 404 Week 5 Risk Management Plan MGMT 404 Week 6 Resource Management Plan MGMT 404 Week 7 Project Coffee Shop Communication Plan MGMT 404 Week 8 Course Project MGMT 404 Complete Course Weeks 1-7 iLabs MGMT404 Week 1 iLab Basics of Project Scheduling MGMT404 Week 2 iLab Managing Project Resources MGMT404 Week 3 iLab Scheduling with Resources MGMT404 Week 4 iLab Working with Calendars MGMT404 Week 5 iLab Resource Workloads MGMT404 Week 6 iLab Task Constraints and......

Words: 786 - Pages: 4

Mgmt-404 Project Management Complete Course

...com/downloads/mgmt-404-project-management-complete-course/ MGMT404 Week 2 Project Selection MGMT 404 Week 3 Scope Statement MGMT 404 Week 4 Work Breakdown Structure and Network Diagram MGMT 404 Week 5 Risk Management Plan MGMT 404 Week 6 Resource Management Plan MGMT 404 Week 7 Project Coffee Shop Communication Plan MGMT 404 Week 8 Course Project MGMT 404 Complete Course Weeks 1-7 iLabs MGMT404 Week 1 iLab Basics of Project Scheduling MGMT404 Week 2 iLab Managing Project Resources MGMT404 Week 3 iLab Scheduling with Resources MGMT404 Week 4 iLab Working with Calendars MGMT404 Week 5 iLab Resource Workloads MGMT404 Week 6 iLab Task Constraints and Baselines MGMT404 Week 7 iLab Tracking Project Progress MGMT-404 Project Management Complete Course http://www.devryguiders.com/downloads/mgmt-404-project-management-complete-course/ MGMT404 Week 2 Project Selection MGMT 404 Week 3 Scope Statement MGMT 404 Week 4 Work Breakdown Structure and Network Diagram MGMT 404 Week 5 Risk Management Plan MGMT 404 Week 6 Resource Management Plan MGMT 404 Week 7 Project Coffee Shop Communication Plan MGMT 404 Week 8 Course Project MGMT 404 Complete Course Weeks 1-7 iLabs MGMT404 Week 1 iLab Basics of Project Scheduling MGMT404 Week 2 iLab Managing Project Resources MGMT404 Week 3 iLab Scheduling with Resources MGMT404 Week 4 iLab Working with Calendars MGMT404 Week 5 iLab Resource Workloads MGMT404 Week 6 iLab Task Constraints and Baselines MGMT404 Week 7 iLab......

Words: 1250 - Pages: 5

Mgmt 404 Project Management Entire Course

...com/downloads/mgmt-404-project-management-entire-course/ MGMT404 Week 2 Project Selection MGMT 404 Week 3 Scope Statement MGMT 404 Week 4 Work Breakdown Structure and Network Diagram MGMT 404 Week 5 Risk Management Plan MGMT 404 Week 6 Resource Management Plan MGMT 404 Week 7 Project Coffee Shop Communication Plan MGMT 404 Week 8 Course Project MGMT 404 Complete Course Weeks 1-7 iLabs MGMT404 Week 1 iLab Basics of Project Scheduling MGMT404 Week 2 iLab Managing Project Resources MGMT404 Week 3 iLab Scheduling with Resources MGMT404 Week 4 iLab Working with Calendars MGMT404 Week 5 iLab Resource Workloads MGMT404 Week 6 iLab Task Constraints and Baselines MGMT404 Week 7 iLab Tracking Project Progress MGMT 404 Project Management Entire Course http://hwguiders.com/downloads/mgmt-404-project-management-entire-course/ MGMT404 Week 2 Project Selection MGMT 404 Week 3 Scope Statement MGMT 404 Week 4 Work Breakdown Structure and Network Diagram MGMT 404 Week 5 Risk Management Plan MGMT 404 Week 6 Resource Management Plan MGMT 404 Week 7 Project Coffee Shop Communication Plan MGMT 404 Week 8 Course Project MGMT 404 Complete Course Weeks 1-7 iLabs MGMT404 Week 1 iLab Basics of Project Scheduling MGMT404 Week 2 iLab Managing Project Resources MGMT404 Week 3 iLab Scheduling with Resources MGMT404 Week 4 iLab Working with Calendars MGMT404 Week 5 iLab Resource Workloads MGMT404 Week 6 iLab Task Constraints and Baselines MGMT404 Week 7......

Words: 1860 - Pages: 8

Mgmt 404 (Project Management) Entire Course - Devry

...com/MGMT-404-Project-Management-Entire-Course-DeVry-1123432.htm?categoryId=-1 If You Face Any Problem E- Mail Us At JohnMate1122@gmail.com MGMT404 Week 1 iLab MGMT404 Week 1 DQ 1 Case Study; A Day in the Life MGMT404 Week 1 DQ 2 Case Study; Moss and McAdams Accounting Firm MGMT404 Week 2 Course Project: Project Selection MGMT404 Week 2 iLab MGMT404 Week 2 DQ 1 Project Scope MGMT404 Week 2 DQ 2 Case Study; Sharp Printing AG MGMT404 Week 3 Course Project: Scope Statement MGMT404 Week 3 iLab MGMT404 Week 3 DQ 1 Project Schedule MGMT404 Week 3 DQ 2 Risk Management MGMT404 Week 4 Course Project: Work Breakdown Structure and Network Diagram MGMT404 Week 4 iLab MGMT404 Week 4 DQ 1 Managing Resource Constraints MGMT404 Week 4 DQ 2 Reducing Project Duration MGMT404 Week 5 Course Project: Risk Management Plan MGMT404 Week 5 iLab MGMT404 Week 5 DQ 1 Project Baseline MGMT404 Week 5 DQ 2 Project Communication MGMT404 Week 6 Course Project: Resource Management Plan MGMT404 Week 6 iLab MGMT404 Week 6 DQ 1 Case Study; Western Oceanography Institute MGMT404 Week 6 DQ 2 Case Study; Kerzner Office Equipment MGMT404 Week 7 Course Project: Communication Plan MGMT404 Week 7 iLab MGMT404 Week 7 DQ 1 Case Study; Buxton Hall MGMT404 Week 7 DQ 2 Case Study; A Day in the Life revisited MGMT404 Week 8 Final Project Package...

Words: 256 - Pages: 2

Mgmt 404 (Project Management) Entire Course - Devry

...com/MGMT-404-Project-Management-Entire-Course-DeVry-1123432.htm?categoryId=-1 If You Face Any Problem E- Mail Us At JohnMate1122@gmail.com MGMT404 Week 1 iLab MGMT404 Week 1 DQ 1 Case Study; A Day in the Life MGMT404 Week 1 DQ 2 Case Study; Moss and McAdams Accounting Firm MGMT404 Week 2 Course Project: Project Selection MGMT404 Week 2 iLab MGMT404 Week 2 DQ 1 Project Scope MGMT404 Week 2 DQ 2 Case Study; Sharp Printing AG MGMT404 Week 3 Course Project: Scope Statement MGMT404 Week 3 iLab MGMT404 Week 3 DQ 1 Project Schedule MGMT404 Week 3 DQ 2 Risk Management MGMT404 Week 4 Course Project: Work Breakdown Structure and Network Diagram MGMT404 Week 4 iLab MGMT404 Week 4 DQ 1 Managing Resource Constraints MGMT404 Week 4 DQ 2 Reducing Project Duration MGMT404 Week 5 Course Project: Risk Management Plan MGMT404 Week 5 iLab MGMT404 Week 5 DQ 1 Project Baseline MGMT404 Week 5 DQ 2 Project Communication MGMT404 Week 6 Course Project: Resource Management Plan MGMT404 Week 6 iLab MGMT404 Week 6 DQ 1 Case Study; Western Oceanography Institute MGMT404 Week 6 DQ 2 Case Study; Kerzner Office Equipment MGMT404 Week 7 Course Project: Communication Plan MGMT404 Week 7 iLab MGMT404 Week 7 DQ 1 Case Study; Buxton Hall MGMT404 Week 7 DQ 2 Case Study; A Day in the Life revisited MGMT404 Week 8 Final Project Package...

Words: 256 - Pages: 2

Mgmt404 Scope Statement

...Project Scope Statement Project Name | BrewBacca’s | Project Number | Bacca’s_001 | Project Manager | Kristin Smallwood | Prioritization | High | Owner(s) | Kristin Smallwood | Statement of Work—Project Description andProject Product | This project is to open a friendly Coffee shop that has an environment set toward the fantasy film genre, as well as serving the finest hand selected coffee. The chosen site is 2450 sq ft. and will have sufficient foot traffic from the offices located around the site. The initial startup fee will cost $27,000.00, of which a investor has already agreed to supply $17,000.00 and I supply the remaining $10,000.00. The site is a fully opened storefront with a food preparation area partition. The monthly rental fee is $3,100.00 and the utilities are $1700.00. | | Project Deliverables | | | Project Objectives | In today’s society bullying is a big problem especially to those who enjoy science fiction fantasy. Here at BrewBacca’s we will unite a common like of science fiction and have an open forum for discussions and topics without social bias all while forming bonds of comradery over a hot cup of joe. | Project Assumptions | * All Hardware is functional * Utilities and Pluming are installed correctly and properly functions * Purchasing top quality coffee and equipment * Employees are properly trained in all equipment | Project Constraints | * Lack of Funding * Location not set in a high foot traffic...

Words: 311 - Pages: 2

Mgmt404 Lesson 3

...Review Questions Answer the following questions (use MS Project help if necessary): 1) Define effort-driven? Effort-driven means that when you assign or remove people from a task, Project lengthens or shortens the duration of the task based on the amount of resource units assigned to it, but it doesn't change the total amount of work for the task. When you add or delete resources on an effort-driven task, work is spread around equally among resources 2) Under what circumstances would you turn off effort driven scheduling? You can turn off the Effort Driven setting if you choose the fixed-duration or fixed-units task type. With the fixed-work task type selected, the Effort Driven setting isn’t only turned on automatically, but in fact it can’t be turned off. 3) Use a real-world example of when you would make a task as a Fixed Duration type task? Your painter is assigned full-time (100%) to paint a room in 4 days. The work is 32 hours. Then you assign the same painter another room to paint. The painter can only work part-time (50%) painting the additional room. When you enter 50%, Project keeps the duration fixed at 4 days, and recalculates work to be 16 hours. 4) What is the formula for calculating duration? Duration = Work ÷ Resource Units 5) What are the eight preset work contours (hint: In the Task Usage view right click on a resource name an open the assignment information box) and what are the procedures in applying them......

Words: 399 - Pages: 2

Dragon Ball – Bảy Viên Ngọc Rồng chap 43 | RIN Daughters of Mnemosyne | Poppy Drayton